The Regional Commissioner-Eastern, accompanied by Meru County Commissioner and Eastern Region-Regional Development Implementation Coordination Committee (RDICC) including TWWDA CEO carried out a project validation visit of Meru Sewerage Project on 15th March, 2022.
The team then inspected ongoing construction of Kiogo trunk and concluded by visiting the ongoing construction of the New Meru Sewerage Treatment Plant, which will De-Commission Gakoromone Treatment Plant. When complete the project will benefit 193,000 people in Meru County.
TWWDA is undertaking a project in Meru county which involves the construction of a new sewerage treatment plant. It is estimated that the new sewerage infrastructure will treat 800m³ of sewer on a daily basis. The project consists of two different series of ponds i.e. Series 1 and series 2 as follow;